ABC Liberia Restoration Schedule

January
February
March
April
May
June
July
August
September
Del arrives in Liberia
January 7, 2008
Purchase and install generator Extend Administration Building

Roof, windows, doors on Admin. Building

Del & Becky in U.S. for month of April   The Grove Church work team first two weeks of June

Women’s Dorm
Ceiling, electrical, plumbing, floor tile, wall tile

Lookout Mtn. Pres. Church work team first two weeks of July

Faculty House #3
Ceiling, electrical, plumbing, floor tile, wall tile

  Open ABC University
Sept. 1, 2008!
SP Project Manager, Dave & Trudy, arrive in Liberia January 20, 2008 Extend Library

Roof, windows, doors on Library

Begin ABC Guest House in Monrovia

Extend Library

Roof, windows, doors on Library


  Grace Pres. Church work team last two weeks of June

Men’s Dorm #2
Ceiling, electrical, plumbing, floor tile, wall tile

Granada Heights Friends Church work team last two weeks of July

Classroom
Ceiling, electrical, floor tile, tables, chairs

Finish ABC Guest House in Monrovia  
Becky arrives in Liberia Feb 2, 2008 SP Work team #1
Feb. 1-20, 2008

Faculty House #2 Ceiling, electrical, ceramic tile flooring and walls, kitchen cupboards and countertop, paint, etc.

SP Work team #2 March 1-20, 2008

Water
Erect water tower and connect water pump from well to tower.

Connect water pump to generator.

Connect water line and electrical line to buildings.

SP Work team #3 April 1-20, 2008

Men’s Dorm #1
Ceiling, electrical, plumbing, floor tile, wall tile

SP Work team #4
May 1-21, 2008

Dining Hall
Ceiling, electrical, plumbing, floor tile, wall tile

    SP Work team #5 Aug 1-30, 2008

Chapel
Roof, windows, doors, ceiling, electrical, plumbing, floor tile, studio

 